Redfield Public School District

Project Overview
This phased project involved vacating a street to accommodate building the kitchen, commons area, and new high school wing. Upon building completion and transfer of students to the new wing, the old building was demolished, and the elementary school was built. Once the new elementary school was completed and students transferred over, then the old elementary building was demolished. Quest utilized innovative measures to finish the interior flatwork before starting on framing the walls. This allowed the plumbers and other subcontractors to get their product installed without the inconvenience of working around the framing crew.
Client Testimonial
Project Details
Location
Redfield, SD
Industry
Education
Project Size
127,777 ft2
Year Completed
2020